Bay Area Rail Plan

The plan · adopted September 26, 2007

The 2007 Bay Area Regional Rail Plan

A 50-year plan for every passenger train in the nine-county Bay Area, written by MTC with BART, Caltrain and the California High-Speed Rail Authority. Adopted by MTC on September 26, 2007.

Why it existed

In 2004 Bay Area voters passed Regional Measure 2, a $1 toll increase on the seven state-owned bridges. The measure also required MTC to adopt a Regional Rail Plan: one network for the whole region, including how high-speed rail would reach it.

Work started in late 2005 with public meetings. A steering committee of Caltrans, Amtrak, the Capitol Corridor, ACE, SMART, the Port of Oakland, Union Pacific, BNSF and the nine county agencies met about every quarter. From 2005 to 2007, this address, bayarearailplan.info, was the project's official website.

What it said

What it would cost

Estimated total capital investment for the plan: about $45 billion (2006 dollars). The later chapters give a slightly different figure: recommended 'hybrid' network: $35B capital + $8B BART Core Capacity = $43B; Resolution 3434 share $10B; ~$1.4B/year operating (Alt 1: $1.6B/yr; Alt 2: $1.3B/yr). 2006 dollars.

High-speed rail into the Bay Area was priced separately: Altamont and Pacheco options each about $16–18 billion (2006), about $1B more to accommodate regional services; Altamont + Pacheco combined about $21 billion.

The timetable it set

Near term, to 2015

Intermediate, 2015–2030

Long term, 2030–2050

From Table 8.2-1 of the final report. The PDF's table columns are hard to read, so a few items may sit one column off; those are flagged in our notes.

How it went

Most of the near-term list arrived late or not at all. See the scorecard for each project, with sources.

  1. 2004 · Regional Measure 2 passes and requires the plan.
  2. Late 2005 · Public outreach meetings begin.
  3. 2006 · Network alternatives are drawn up and tested.
  4. 2007-09-26 · MTC adopts the final plan.
  5. 2014–2020 · Oakland Airport Connector, BART Warm Springs, eBART, SMART, Salesforce Transit Center and BART Berryessa open.
  6. 2024-09-21 · Caltrain runs fully electric between San Francisco and San José.
  7. 2025–2026 · A second BART tube is dropped; BART Phase II and The Portal still wait for federal grant agreements.

Read the original